Critical
Duration
Projected
Start
Projected
Completion
Description
Lot Clearing
1
Day Jan 1, 2010 Jan 2, 2010
Stake House Corners
1
Day Jan 2, 2010 Jan 3, 2010
Foundation
7
Days Jan 3, 2010 Jan 10, 2010
Termite Treatment
0
Days Jan 10, 2010 Jan 10, 2010
Garage Floor
1
Day Jan 10, 2010 Jan 11, 2010
Lumber/Truss Delivery
0
Days Jan 11, 2010 Jan 11, 2010
Framing
50
Days Jan 11, 2010 March 2, 2010
Rough Plumbing
3
Days March 2, 2010 March 5, 2010
Fireplace
0
Days March 5, 2010 March 5, 2010
Rough H.V.A.C.
4
Days March 5, 2010 March 9, 2010
Roofing Installation
3
Days March 9, 2010 March 12, 2010
Rough Electrical
4
Days March 12, 2010 March 16, 2010
Rough Low Voltage
1
Day March 16, 2010 March 17, 2010
Batt Insulation
2
Days March 17, 2010 March 19, 2010
Exterior Deck/Patios
0
Days March 19, 2010 March 19, 2010
Soffits and Facia
0
Days March 19, 2010 March 19, 2010
Brick Veneer
10
Days March 19, 2010 March 29, 2010
Drywall
18
Days March 29, 2010 April 16, 2010
Wood Flooring
3
Days April 16, 2010 April 19, 2010
Interior Trim/Handrails
10
Days April 19, 2010 April 29, 2010
Mantle/Marble
0
Days April 29, 2010 April 29, 2010
Prep and Prime Walls
5
Days April 29, 2010 May 4, 2010
Drywall Point-Up
5
Days May 4, 2010 May 9, 2010
Paint Spray/Roll
5
Days May 9, 2010 May 14, 2010
Cabinet Installation
4
Days May 14, 2010 May 18, 2010
Garage Door
0
Days May 18, 2010 May 18, 2010
Cultured Marble
1
Day May 18, 2010 May 19, 2010
Driveway/Flatwork
2
Days May 19, 2010 May 21, 2010
Final grade/Landscaping
5
Days May 21, 2010 May 26, 2010
Gutters and Downspouts
0
Days May 26, 2010 May 26, 2010
Ceramic Tile
3
Days May 26, 2010 May 29, 2010
Blown Insulation
2
Days May 29, 2010 May 31, 2010
Appliances
0
Days May 31, 2010 May 31, 2010
Plumbing Trim
3
Days May 31, 2010 June 3, 2010
H.V.A.C. Trim
3
Days June 3, 2010 June 6, 2010
Electric Trim
3
Days June 6, 2010 June 9, 2010
Low Voltage Trim
2
Days June 9, 2010 June 11, 2010
Interior Hardware
0
Days June 11, 2010 June 11, 2010
Mirrors & Enclosures
1
Day June 11, 2010 June 12, 2010
Window Screens
0
Days June 12, 2010 June 12, 2010
Closet Shelving
1
Day June 12, 2010 June 13, 2010
Iron Railing
0
Days June 13, 2010 June 13, 2010
Carpeting
3
Days June 13, 2010 June 16, 2010
Final Painting
5
Days June 16, 2010 June 21, 2010
Final Cleaning
2
Days June 21, 2010 June 23, 2010
Pressure Washing
0
Days June 23, 2010 June 23, 2010
Orientation/Punch Out
7
Days June 23, 2010 June 30, 2010

Total Projected Time
Estimated Total Construction Duration (Days):180 Days
Estimated Total Construction Duration (Months): 6 Months
Estimated Completion Date: June 30, 2010
Events that require zero (0) days are not in the critical path


Hollison Custom Homes
1200 Woodruff Road Suite A-3
Greenville, SC 29607
P: 864.527.6819
F: 864.322.7875

"I have built a home with another builder in the past and experienced the old adage 'Price, Quality or Delivery -pick any two'. With Hollison Homes, I came to realize that you truly can get all three."
Chuck & Teri Henry