Critical
Duration
Projected
Start
Projected
Completion
Description
Lot Clearing
1
Day Jan 1, 2008 Jan 2, 2008
Stake House Corners
1
Day Jan 2, 2008 Jan 3, 2008
Foundation
7
Days Jan 3, 2008 Jan 10, 2008
Termite Treatment
0
Days Jan 10, 2008 Jan 10, 2008
Garage Floor
1
Day Jan 10, 2008 Jan 11, 2008
Lumber/Truss Delivery
0
Days Jan 11, 2008 Jan 11, 2008
Framing
50
Days Jan 11, 2008 March 2, 2008
Rough Plumbing
3
Days March 2, 2008 March 5, 2008
Fireplace
0
Days March 5, 2008 March 5, 2008
Rough H.V.A.C.
4
Days March 5, 2008 March 9, 2008
Roofing Installation
3
Days March 9, 2008 March 12, 2008
Rough Electrical
4
Days March 12, 2008 March 16, 2008
Rough Low Voltage
1
Day March 16, 2008 March 17, 2008
Batt Insulation
2
Days March 17, 2008 March 19, 2008
Exterior Deck/Patios
0
Days March 19, 2008 March 19, 2008
Soffits and Facia
0
Days March 19, 2008 March 19, 2008
Brick Veneer
10
Days March 19, 2008 March 29, 2008
Drywall
18
Days March 29, 2008 April 16, 2008
Wood Flooring
3
Days April 16, 2008 April 19, 2008
Interior Trim/Handrails
10
Days April 19, 2008 April 29, 2008
Mantle/Marble
0
Days April 29, 2008 April 29, 2008
Prep and Prime Walls
5
Days April 29, 2008 May 4, 2008
Drywall Point-Up
5
Days May 4, 2008 May 9, 2008
Paint Spray/Roll
5
Days May 9, 2008 May 14, 2008
Cabinet Installation
4
Days May 14, 2008 May 18, 2008
Garage Door
0
Days May 18, 2008 May 18, 2008
Cultured Marble
1
Day May 18, 2008 May 19, 2008
Driveway/Flatwork
2
Days May 19, 2008 May 21, 2008
Final grade/Landscaping
5
Days May 21, 2008 May 26, 2008
Gutters and Downspouts
0
Days May 26, 2008 May 26, 2008
Ceramic Tile
3
Days May 26, 2008 May 29, 2008
Blown Insulation
2
Days May 29, 2008 May 31, 2008
Appliances
0
Days May 31, 2008 May 31, 2008
Plumbing Trim
3
Days May 31, 2008 June 3, 2008
H.V.A.C. Trim
3
Days June 3, 2008 June 6, 2008
Electric Trim
3
Days June 6, 2008 June 9, 2008
Low Voltage Trim
2
Days June 9, 2008 June 11, 2008
Interior Hardware
0
Days June 11, 2008 June 11, 2008
Mirrors & Enclosures
1
Day June 11, 2008 June 12, 2008
Window Screens
0
Days June 12, 2008 June 12, 2008
Closet Shelving
1
Day June 12, 2008 June 13, 2008
Iron Railing
0
Days June 13, 2008 June 13, 2008
Carpeting
3
Days June 13, 2008 June 16, 2008
Final Painting
5
Days June 16, 2008 June 21, 2008
Final Cleaning
2
Days June 21, 2008 June 23, 2008
Pressure Washing
0
Days June 23, 2008 June 23, 2008
Orientation/Punch Out
7
Days June 23, 2008 June 30, 2008

Total Projected Time
Estimated Total Construction Duration (Days):180 Days
Estimated Total Construction Duration (Months): 6 Months
Estimated Completion Date: June 30, 2008
Events that require zero (0) days are not in the critical path


Hollison Custom Homes , LLC
1200 Woodruff Road Suite A-3
Greenville, SC 29607
P: 864.527.6819
F: 864.322.7875

"I have built a home with another builder in the past and experienced the old adage 'Price, Quality or Delivery -pick any two'. With Hollison Homes, I came to realize that you truly can get all three."
Chuck & Teri Henry