| Critical Duration |
Projected Start |
Projected Completion |
|
| Description |
| Lot Clearing | 1 |
Day | Jan 1, 2008 | Jan 2, 2008 |
| Stake House Corners | 1 |
Day | Jan 2, 2008 | Jan 3, 2008 |
| Foundation | 7 |
Days | Jan 3, 2008 | Jan 10, 2008 |
| Termite Treatment | 0 |
Days | Jan 10, 2008 | Jan 10, 2008 |
| Garage Floor | 1 |
Day | Jan 10, 2008 | Jan 11, 2008 |
| Lumber/Truss Delivery | 0 |
Days | Jan 11, 2008 | Jan 11, 2008 |
| Framing | 50 |
Days | Jan 11, 2008 | March 2, 2008 |
| Rough Plumbing | 3 |
Days | March 2, 2008 | March 5, 2008 |
| Fireplace | 0 |
Days | March 5, 2008 | March 5, 2008 |
| Rough H.V.A.C. | 4 |
Days | March 5, 2008 | March 9, 2008 |
| Roofing Installation | 3 |
Days | March 9, 2008 | March 12, 2008 |
| Rough Electrical | 4 |
Days | March 12, 2008 | March 16, 2008 |
| Rough Low Voltage | 1 |
Day | March 16, 2008 | March 17, 2008 |
| Batt Insulation | 2 |
Days | March 17, 2008 | March 19, 2008 |
| Exterior Deck/Patios | 0 |
Days | March 19, 2008 | March 19, 2008 |
| Soffits and Facia | 0 |
Days | March 19, 2008 | March 19, 2008 |
| Brick Veneer | 10 |
Days | March 19, 2008 | March 29, 2008 |
| Drywall | 18 |
Days | March 29, 2008 | April 16, 2008 |
| Wood Flooring | 3 |
Days | April 16, 2008 | April 19, 2008 |
| Interior Trim/Handrails | 10 |
Days | April 19, 2008 | April 29, 2008 |
| Mantle/Marble | 0 |
Days | April 29, 2008 | April 29, 2008 |
| Prep and Prime Walls | 5 |
Days | April 29, 2008 | May 4, 2008 |
| Drywall Point-Up | 5 |
Days | May 4, 2008 | May 9, 2008 |
| Paint Spray/Roll | 5 |
Days | May 9, 2008 | May 14, 2008 |
| Cabinet Installation | 4 |
Days | May 14, 2008 | May 18, 2008 |
| Garage Door | 0 |
Days | May 18, 2008 | May 18, 2008 |
| Cultured Marble | 1 |
Day | May 18, 2008 | May 19, 2008 |
| Driveway/Flatwork | 2 |
Days | May 19, 2008 | May 21, 2008 |
| Final grade/Landscaping | 5 |
Days | May 21, 2008 | May 26, 2008 |
| Gutters and Downspouts | 0 |
Days | May 26, 2008 | May 26, 2008 |
| Ceramic Tile | 3 |
Days | May 26, 2008 | May 29, 2008 |
| Blown Insulation | 2 |
Days | May 29, 2008 | May 31, 2008 |
| Appliances | 0 |
Days | May 31, 2008 | May 31, 2008 |
| Plumbing Trim | 3 |
Days | May 31, 2008 | June 3, 2008 |
| H.V.A.C. Trim | 3 |
Days | June 3, 2008 | June 6, 2008 |
| Electric Trim | 3 |
Days | June 6, 2008 | June 9, 2008 |
| Low Voltage Trim | 2 |
Days | June 9, 2008 | June 11, 2008 |
| Interior Hardware | 0 |
Days | June 11, 2008 | June 11, 2008 |
| Mirrors & Enclosures | 1 |
Day | June 11, 2008 | June 12, 2008 |
| Window Screens | 0 |
Days | June 12, 2008 | June 12, 2008 |
| Closet Shelving | 1 |
Day | June 12, 2008 | June 13, 2008 |
| Iron Railing | 0 |
Days | June 13, 2008 | June 13, 2008 |
| Carpeting | 3 |
Days | June 13, 2008 | June 16, 2008 |
| Final Painting | 5 |
Days | June 16, 2008 | June 21, 2008 |
| Final Cleaning | 2 |
Days | June 21, 2008 | June 23, 2008 |
| Pressure Washing | 0 |
Days | June 23, 2008 | June 23, 2008 |
| Orientation/Punch Out | 7 |
Days | June 23, 2008 | June 30, 2008 |
Total Projected Time
Estimated Total Construction Duration (Days):180 DaysEstimated Total Construction Duration (Months): 6 Months
Estimated Completion Date: June 30, 2008
Events that require zero (0) days are not in the critical path
Hollison Custom Homes , LLC
1200 Woodruff Road Suite A-3
Greenville, SC 29607
P: 864.527.6819
F: 864.322.7875
"I have built a home with another builder in the past and experienced the old adage 'Price, Quality or Delivery -pick any two'. With Hollison Homes, I came to realize that you truly can get all three."
Chuck & Teri Henry